VIDEO | Md. Launches $28 Million Chesapeake Bay Crossing Tier 2 Study

bongino-promo

Maryland is launching a $28-million Bay Crossing Tier Two Study.
Governor Larry Hogan said Friday that this phase will study the new Bay Bridge Crossing, and it will address traffic impact at the new crossing but also for miles in each direction, including the 50 / 301 split.

Back in April, What is known as ‘Corridor 7’ emerged as the most viable option following a review conducted by the Maryland Transportation Authority. The corridor is near the two bridges between Queen Anne’s County and the Annapolis area.

“At my direction, we are immediately launching a critical $28 million Bay Crossing Tier 2 Study, which will not only study the new crossing, but also look at solutions for the entire 22-mile corridor from the Severn River Bridge to the 50/301 split,” Hogan said. “This is the critical next step which is needed in order to move forward so we can make a new Bay crossing a reality in the years to come, and it is just one more way that together we are truly changing Maryland for the better.”

Governor Larry Hogan announced a Chesapeake Bay crossing study development Friday June 10th 2022.

“The $28 million Tier 2 study will build upon the Tier 1 findings and identify specific alignment alternatives within Corridor 7, which is two miles wide and 22 miles long, from the Severn River Bridge in Anne Arundel County to the US 50/US 301 split in Queen Anne’s County,” MDTA Chairman and Md. Transportation Secretary James Ports Jr. said. “The Tier 2 study will identify and evaluate a No-Build Alternative as well as various crossing alignments and types—such as a new bridge, a bridge/tunnel or replacement of existing spans. We’re eager to engage with residents, communities, officials, stakeholders and other members of the public on the Tier 2 Study. As we learned from the Tier 1 Study, the public’s contributions in this process are invaluable.”

Governor Larry Hogan’s office provided additional background:

At its June 23 meeting, the MDTA Board is expected to vote on the agency’s draft Consolidated Transportation Program, which includes funding for the Tier 2 NEPA. The study would take about four to five years to complete. If a build alignment alternative is selected, another Record of Decision for Tier 2 would be required before proceeding to final design, right-of-way acquisition, and construction. A No-Build Alternative means that no action of any kind would be taken.

“Today’s announcement marks a major milestone for Maryland that advances a path forward for congestion relief at the Bay Bridge and for local communities in Anne Arundel and Queen Anne’s counties,” MDTA Executive Director William Pines said.

Modal and operational alternatives (MOA), including ferry service, rail, bus, and transportation system management/transportation demand management were evaluated as part of Tier 1 and were found to not meet the Tier 1 purpose and need as stand-alone options. The Tier 2 study will analyze buses, ferries, and transportation system and demand management, as well as how they may be used in conjunction with other alternatives.

Additional information and public participation opportunities for the Tier 2 NEPA Study will be posted to baycrossingstudy.com.

Bay Bridge Progress Saves Customers Time, Money. The launch of the Bay Crossing Study Tier 2 NEPA is the latest milestone in Governor Hogan’s commitment to make the Chesapeake Bay crossing safer, more efficient, and more affordable for Marylanders and visitors to the state. Since 2015, the Hogan Administration has eliminated the $1.50 E-ZPass monthly fee for Maryland residents, made E-ZPass transponders free, and reduced tolls twice—delivering a $2.50 E-ZPass Maryland toll at the Bay Bridge, which is a less expensive round trip toll price than when the bridge opened in 1952.

Additionally, the governor launched and completed the Tier 1 NEPA phase of the Bay Crossing Study and broke a bottleneck at the Severn River Bridge by adding a fourth lane eastbound—a project recognized with national awards. Under the governor’s direction, the MDTA also completed the two-year Bay Bridge westbound re-decking project in seven months, a year ahead of schedule; removed toll booths at the bridge; and implemented highway-speed all-electronic tolling years ahead of schedule.

The MDTA also launched construction of a new Automated Lane Closure System at the Bay Bridge to provide more efficient conversion to two-way operations. The new system will improve traffic operations and safety for employees by replacing the barrel-and-cone system.