Work Begins Monday on Eventual Replacement of Route 54 Bridge West of Fenwick Island
January 4, 2026/
Expect delays on Route 54/Lighthouse Road beginning Monday as lane closures can be expected until the end of April. This is the start of the replacement of the Route 54 bridge . The work that starts this week will take place between Van Buren and Dukes Avenues.聽 This project is expected to be completed by late summer of 2028.聽聽
DelDOT has scheduled work hours for this part of the project –聽
- Sunday 7p to Monday 12p聽
- Monday 4p to Tuesday 4p
- Tuesday 6p to Wednesday 4p
- Wednesday 6p to Thursday 4p
- Thursday 6p to Friday 10a
- Friday 8p to Saturday 9a
- Saturday 7p to Sunday 9a
For more information – go to the project website.聽聽